Friday, 6 October 2017
Lathe Machine
Lathe machine
Date:-18 july 2017
Lathe machine:-
1) Turning:-turning means if any object like wood, metal are decrease thickness is called turning. we use tool and make a design in wood and metal.
2)Boring:-we use boring tools and increase the size of hole.
3)Knurling:- use knurling tool to make a grip in metal.
4)Tapering:- in lathe machine use tap set to tapping a metal and threading.
Images:-
Date:-18 july 2017
Lathe machine:-
1) Turning:-turning means if any object like wood, metal are decrease thickness is called turning. we use tool and make a design in wood and metal.
2)Boring:-we use boring tools and increase the size of hole.
3)Knurling:- use knurling tool to make a grip in metal.
4)Tapering:- in lathe machine use tap set to tapping a metal and threading.
Images:-
part
of lathe machine:-belt drive, gear box, head stock, three jaw chuck,
job, tools, spindle, chuck, lead screw, handle, tail stock, bed etc
Cost:-1,10,000
Base Line Out
Base line out
Aim:- How to make and marking base line
using of material:-
Images:-
Date:-01 August 2017
Aim:- How to make and marking base line
Requirement:- thread, line tube, spirit lavel, valmba, torshan bar, hammer and white powder.
procedure:- 1)Fix bar one side and give measurement and fix bar another side.
2) In square type of measurement we fix 8 nos of bar then attached with thread .
3) Take right angle then we measure one side 4 mtr second side 3 mtr and last one give 5mtr .
using of material:-
Thread:- we use thread to fix our base line
line tube:- we use line tube to make a perfect measurement to one side to another side.
valamba :- use of valamba to our pole is fix in centre
Images:-
To prepare R.C.C Column
To Prepare R.C.C Column
Date:-10 Sept 2017
Aim:- To Prepare R.C.C Column.
Requirement:-Tools and equipment measuring tape, thapi, khore, gunny bags,etc
Materials:-8mm torshan bar, 6 mm bar, sand, gravels, cement, water, etc
Procedure:- 1) Take torshan bar 8 mm and 6 mm bar make frame and ring
2) Mix cement, gravels, sand, prepare concrete
3)Take molde and fix torshan bar and fill with concrete
4) use G.I wire to roped it a molde
Costing of materials:-
Sr.no
|
MATERIALS
|
QTY
|
RATE
|
AMOUNT
|
1
|
SAND
|
4 TOPLI
|
15 PER
|
60
|
2
|
GRAVELS
|
2 TOPLI
|
12 PER
|
24
|
3
|
CEMENT
|
2 TOPLI
|
8 PER
|
112
|
4
|
TORSHAN BAR 8 MM
|
1.931kg
|
48 KG
|
92.68
|
5
|
TORSHAN BAR 6 MM
|
0.222kg
|
48 KG
|
92.68
|
WORKING CHARGE 25%
|
95.34
| |||
TOTAL
|
476.70
|
images:-
Subscribe to: